It’s full steam ahead on site following all of the bad weather in November and December 2022. The bricklayer was able to complete all brickwork and internal blockwork and the roof truss works continue.
The completion date for the building has now moved to 22nd May 2023, an extension to the contract of 4 weeks to reflect the exceptionally inclement weather (rain and frost) in the period before Christmas.