• Hethersett Pavilion Update – May 2023

    We’re excited to see how the build of this great community asset is progressing! You can now see it all coming together in the following pictures.

    • Containers to be taken off site 24th May.
    • Disabled car park markings and access gate hatching 24th May.

  • Hethersett Pavilion Building Update – 19/01/23

    Despite the freezing weather we have progressed with the roof trusses and completed the facias and soffits. The block laying to gables was stopped due to cold weather. External scaffold to be raised this week for roofer and the
    Internal scaffolding to be struck next week. Roof coverings to commence Monday (subject to weather) and the small amount of water in swale has frozen over. We are currently scheduled for completion of the build by 22nd May 2023 (weather permitting).

     

  • 160123 – Hethersett Pavilion Building Update

    It’s full steam ahead on site following all of the bad weather in November and December 2022. The bricklayer was able to complete all brickwork and internal blockwork and the roof truss works continue.

    The completion date for the building has now moved to 22nd May 2023, an extension to the contract of 4 weeks to reflect the exceptionally inclement weather (rain and frost) in the period before Christmas.

  • *UPDATE* HETHERSETT PAVILION BUILDING PROJECT – 8th December 2022

    *UPDATE* HETHERSETT PAVILION BUILDING PROJECT

    Please see the latest update from the Site Manager:

    – Works to footpath alongside the bund have now been postponed until late Jan/Feb (to coincide with car park extension works) due to boggy ground conditions and risk of abortive work with stoning of new path becoming contaminated with mud before the tarmac capping is laid.
    – The external brickwork and blockwork is now up to roof plate level at changing room end.
    – The external blockwork to hall end in progress up to roof plate height. Completion of all brickwork and blockwork still expected end of this week, subject to weather
    – The Internal scaffolding to hall end being erected
    – Internal blockwork being taken up to ceiling height this week with completion of changing room end so roof truss works can commence
    – Roof trusses being moved around the site with roof truss installation now to commence Monday next week
    – Lifting of roof trusses into position expected before Christmas but now unlikely that felt and battens will all be on before Christmas
    – More days lost due to frequent rain showers
    – Ovamill to return this week to extend water pipe to back of kerb – This will involve digging through the hedge
    Ovamill to dig trial hole approx halfway along the pipe installed to demonstrate this is at the correct depth
    *The Anglian Water Road closure is booked for 12th to 15th December (tbc subject to the above works)*

     

  • Rain, rain go away!

    It’s all been very frustrating with all the rain, but it is still hoped to have the roof trusses up and the felt and battening complete by Christmas (subject to weather). In the meantime, here’s an update on what has been completed since the last update:

    • Brickwork and blockwork continuing at hall end
    • Brickwork and blockwork delayed by bad weather. Completion of all brickwork expected in 2 weeks, subject to weather
    • Scaffolding to changing room end delayed by 4 days but should now be in place
    • 4 to 5 days days lost due to heavy rain, bricklayer working Saturday mornings to catch up.

  • Pavilion Update 17th November 2022

    The Pavilion work is proceeding despite several more days lost due to heavy rain. The good news is that the brickwork and blockwork is continuing at the hall end and should be up to the first scaffold lift by Monday.

    The steel wind posts to the hall are now erected as well as the temporary field gate.

    Scaffolding to the changing room end is ready for final brickwork to commence w/c 21st November.

  • November 2022 Pavilion Update

    Despite it been a soggy week, the pavilion project is successfully progressing towards the proposed April 2023 launch date. The brickwork and blockwork is now at the ref’s room and accessible changing area with wind posts being erected to the hall area in advance of brickwork.

    The final connection of the private sewer to the adoptable sewer is underway near the boundary. The trenching through the playing field is completed and re-instated and the pumping chamber is now installed.

    The Ovamill contractors will now sweep the car park and vacate the site until February 2023 when they will return to install the pump controls kiosk.